NGEN has commissioned a 9.4 MW / 18.8 MWh battery storage system in Łozienica, West Pomerania — the first in Poland connected directly to the distribution network operator's grid.

NGEN has commissioned a 9.4 MW / 18.8 MWh battery energy storage system in Łozienica, in Poland's West Pomerania region. Known as Project Vistula, it is the second utility-scale battery storage installation in Poland and the first connected directly to the distribution network operator's grid. The system uses five Tesla Megapack 2XL units — the first deployment of that technology on the Polish market. Operational readiness was confirmed in cooperation with Enea Operator.

Project Vistula was developed as a pilot to demonstrate how large-scale storage can be integrated into the Polish electricity system and its market structures. While storage technology is expanding rapidly across Europe, integration with national grid infrastructure and market rules remains one of the main barriers in emerging storage markets. Connecting at distribution rather than transmission level raised a specific set of questions around communication, control, interconnection, settlement and distribution agreements — questions the project was built to answer in practice.

The installation is integrated with NGEN's digital operating platform, combining SCADA monitoring with ESGP, the group's AI-driven high-level energy management system. The platform enables real-time monitoring and control of the asset, automated optimisation of dispatch against market signals, and coordination between storage operation and grid requirements. The battery operates as an active grid asset, responding to both market conditions and system needs.

Unlike many storage projects, where development, investment and operation sit with separate entities, NGEN acts as investor, owner and operator. This vertically integrated approach allows a single party to carry responsibility from grid connection through to market participation.

Vistula 1

Projects & Milestones
05. September 2026

NGEN builds 70 MW / 140 MWh battery system at Talum

NGEN is deploying a 70 MW / 140 MWh battery energy storage system at Talum in Kidričevo, built with 36 Tesla Megapack 2XL units and operated for ancillary services and energy trading.
Read more
Projects & Milestones
05. September 2026

Uniper and NGEN break ground on 50 MW battery in Wilhelmshaven

Uniper and NGEN have started construction of a 50 MW / 100 MWh grid-connected battery storage facility on the site of a former coal-fired power plant in Wilhelmshaven, Germany.
Read more
Projects & Milestones
05. September 2026

NGEN starts construction of 85 MW / 170 MWh storage in Austria

NGEN has broken ground in Wagenham, Upper Austria, on an 85 MW / 170 MWh battery energy storage system — the largest system-critical storage facility in the country and one of the largest in Europe.