Solker — 1.2 MW solar plant + NGEN storage
- 1.2 MW (grown from a planned 300 kW)Solar capacity800 kW / 1,600 kWhBattery storage
- 2–3× higher financial effectMain resultTime-shifting salesBattery role

The starting point
An investor-owned 1.2 MW solar plant that sold everything at the moment of production.
Owners TEH-SVET and TRING took over the project at a planned 300 kW and developed it to 1.2 MW. Without storage, all output went to the market as it was produced, mostly at midday. The plant had no way to choose when to sell.
The Challenge
When every solar plant sells at noon, noon is when electricity is worth least.
A decade ago, more output meant more revenue. With so much solar now on the grid, prices are often lowest exactly when production peaks, and at times they turn negative.
The owners' analysis of market prices was clear: production alone would not deliver the expected return. They needed a way to hold energy back and sell it when it is worth more.
Where the Saving Comes From
Three things, working together.
Shifting energy in time
The plant was upgraded with an NGEN battery storage system. Electricity produced at midday, when prices are low, is stored and released later, when its market value is higher.
A decision every moment
The control system continuously weighs market conditions, the battery's state of charge and other inputs. It decides whether to send energy to the grid now or store it for later.
From producer to active energy manager
Forecasts of production and prices now matter as much as panel capacity. Solker estimates that solar plants without storage often realise €25–50/MWh. With storage and active management, Solker has averaged around €117/MWh.
According to Dr Karol Peršolja, director of ENER-PRO and co-creator of the project, the expected results would not have been possible without storage. He puts the financial effect at two to three times that of selling at the moment of production.